Dettaglio cantiere

PIAZZALE CADUTI DELLA MONTAGNOLA

AttivoValore contratto 842,00Prodotto € 50.837,33Margine € -3.206,46
← Cantieri
Avanzamento su contratto
100%

Inserimenti settimanalisettimana lunedì→domenica

Settimana (lun)ProduzioneSubappaltiMaterialeManodoperaMargineProgressivo
29/09/20254.024,420,00952,231.600,001.472,194.024,42
06/10/202511.817,420,00965,613.600,007.251,8115.841,84
13/10/20254.930,000,001.425,503.400,00104,5020.771,84
20/10/20257.850,000,001.869,353.600,002.380,6528.621,84
27/10/202512.193,490,00235,813.600,008.357,6840.815,33
03/11/20255.737,500,001.996,183.200,00541,3246.552,83
10/11/20253.442,500,00484,113.200,00-241,6149.995,33
17/11/20250,000,00416,261.400,00-1.816,2649.995,33
24/11/20250,000,00503,002.100,00-2.603,0049.995,33
01/12/20250,000,00799,362.000,00-2.799,3649.995,33
08/12/20250,000,00620,415.400,00-6.020,4149.995,33
05/01/2026842,000,0045,85800,00-3,8550.837,33
26/01/20260,000,006.006,671.400,00-7.406,6750.837,33
02/02/20260,000,00129,511.000,00-1.129,5150.837,33
09/02/20260,000,0022,54600,00-622,5450.837,33
23/02/20260,000,0053,98400,00-453,9850.837,33
02/03/20260,000,0017,42200,00-217,4250.837,33