Dettaglio cantiere

VIA PORTUENSE 95/E

AttivoValore contratto 15.090,00Prodotto € 55.536,01Margine € 23.816,12
← Cantieri
Avanzamento su contratto
100%

Inserimenti settimanalisettimana lunedì→domenica

Settimana (lun)ProduzioneSubappaltiMaterialeManodoperaMargineProgressivo
14/07/20253.913,000,000,001.425,102.487,903.913,00
21/07/20254.549,000,000,001.140,003.409,008.462,00
28/07/202510.657,500,000,005.101,855.555,6519.119,50
04/08/20257.719,000,000,003.444,004.275,0026.838,50
11/08/20254.199,600,000,001.318,402.881,2031.038,10
13/10/2025900,000,001.210,06800,00-1.110,0631.938,10
20/10/20250,000,0045,700,00-45,7031.938,10
03/11/20250,000,00230,720,00-230,7231.938,10
10/11/20258.508,000,000,004.700,003.808,0040.446,10
19/01/20264.838,400,000,003.500,001.338,4045.284,50
26/01/20261.183,210,001.354,10284,86-455,7546.467,71
02/02/20263.019,450,0011,71800,002.207,7449.487,16
09/02/20261.212,500,000,00800,00412,5050.699,66
16/02/20263.091,000,00319,662.000,00771,3453.790,66
23/02/2026877,580,00421,371.547,71-1.091,5054.668,24
09/03/20260,000,00693,26546,33-1.239,5954.668,24
16/03/2026867,770,003,9621,10842,7155.536,01